Wokingham planners voted eight to one for up to 850 homes at Priors Farm. Permission still waits on a legal agreement due within six months.
Up to 850 homes on farmland south of Wokingham have been backed by the borough’s planning committee. Councillors voted eight to one, with no abstentions, to accept officers’ recommendation for Priors Farm on Wednesday 11 November.
The vote can be heard at the end of the council’s own recording of the meeting. The committee has nine members. The minutes have not yet been published, and the planning register still lists application 241933 as “Recommendation Made”.
Overview
The committee resolved to grant permission, but the permission is not issued yet. It depends on a section 106 legal agreement. That agreement can only be completed together with approval of three linked applications, which have not been decided. If it is not signed within six months of the vote, officers are authorised to refuse the scheme, unless they agree more time. The site is the land west of Old Wokingham Road, either side of Easthampstead Road.
What was approved
The applicant is Lightwood Strategic. The site covers 55.79 hectares of mainly farmland (officer report, application 241933).
It is a hybrid application. The homes have outline permission, with only the access fixed. The new public green space has full permission. The scheme includes:
- up to 850 homes, of which up to 340 (40%) would be affordable
- a neighbourhood centre of up to 2,000 square metres
- a 1.03-hectare site for a one-form-entry primary school, if the council decides it needs one
- 31.11 hectares of public open space, including about 20.17 hectares of Suitable Alternative Natural Greenspace (SANG), with a car park
- play areas and allotments
The council’s preferred split for the affordable homes is 70% social rent and 30% shared ownership. At the full 340 homes, the report says that would be about 238 social rent homes and 102 shared ownership homes.
The roads
Easthampstead Road would stop being a through route. The legal agreement covers its partial closure with “modal filters”, so it serves walkers and cyclists. A new junction would be built onto Old Wokingham Road, with an access road through to Byway 30 before the 200th home is occupied.
Bracknell Forest Council’s highways objection still stood when the report was written. It said the impact on its roads “has not been properly assessed, agreed or mitigated”. Officers answered that the key matters can be secured through planning conditions and the legal agreement. Sport England also had a holding objection over sports provision. Officers say a contribution to a new sports hub at Grays Farm will be secured instead.
The report records 218 objections and 3 letters of support. Wokingham Without Parish Council said it “remains opposed”, and Crowthorne Parish Council, over the border in Bracknell Forest, also objected. The Environment Agency, Natural England, National Highways and Thames Water did not object.
What the developer must pay for
The legal agreement’s heads of terms run to 45 items. Among them are contributions to:
- secondary school places
- GP and other health facilities
- a bus service for the south Wokingham area
- walking and cycling links to Wokingham town centre and Bracknell
- the Grays Farm sports hub
- off-site burial grounds
What it means for you
- Nothing is built yet. Each phase of the homes will need a reserved matters application, and each one will be open for comment on the planning register.
- Three linked applications are still to come. These are up to 180 homes on adjoining land (242279), a vehicle crossing of Byway 30 (242051) and up to 95 homes with six Gypsy and Traveller pitches off Old Wokingham Road (211033). The legal agreement cannot be completed until they are approved too.
- The six-month clock runs to May 2027. If the agreement is not signed by then, and officers do not extend it, the application is to be refused.
- The Easthampstead Road closure needs its own order. The agreement lists any traffic regulation orders the scheme needs. Those are advertised for comment separately.
Our earlier report has the full background to the application, including what objectors said and the wider South Wokingham extension.
Have your say